How Long Does It Take to Build a Home in Ontario?
- LUMA Build Design
- Sep 22
- 3 min read
Updated: 4 days ago
The Average Timeline to Build a Home in Ontario
Building a new home is one of the biggest projects a homeowner will ever take on, and one of the most common questions we hear at LUMA Build Design is: “How long does it take?”
On average, a custom home in Ontario takes 10 to 16 months from start to finish. The exact timeline depends on design complexity, permit approvals, and construction details. In areas like Fergus and Elora, where custom homes are popular, timelines can vary, but most follow the same general stages.

Step 1 — Permits & Design (1–3 Months)
Before construction begins, homeowners need architectural designs and building permits. In Centre Wellington, permits are issued by the township and can take 4–8 weeks depending on the project’s scope.
Design stage: Working with an architect or designer to finalize floor plans.
Permit stage: Submitting applications, site plans, and engineering drawings.
Delays: Missing paperwork or revisions requested by the township can extend this step.
Step 2 — Site Prep & Foundation (1–2 Months)
Once permits are approved, the site is prepared for construction.
Excavation: Clearing the lot, grading, and digging for the foundation.
Foundation work: Pouring footings, building forms, and curing concrete.
Weather factors: Cold Ontario winters and heavy rain can delay this stage.
In Fergus and Elora, where many properties sit on unique terrain, extra time may be needed for soil testing or drainage solutions.
Step 3 — Framing & Exterior Work (2–3 Months)
The home starts to take shape as the framing goes up.
Framing: Walls, floors, and roof structures are built.
Exterior: Roofing, windows, and doors are installed to “weather-tight” the home.
Inspection: Township inspectors ensure framing and structural integrity meet code.
At this stage, homeowners can really start to see their home design come to life.

Step 4 — Interior Finishes (3–5 Months)
The interior work is the most detailed and time-consuming part of home building.
Plumbing, electrical, HVAC: Installed and inspected.
Insulation & drywall: Prepares the home for finishes.
Flooring, cabinetry & trim: Custom choices can extend timelines, especially if materials are special order.
Painting & final finishes: The last layer of personality goes into the space.
In custom homes, interior finishes often determine whether a build takes closer to 12 months or 16 months.
Step 5 — Final Inspections & Move-In (1 Month)
Before move-in, the township requires a final inspection to issue an occupancy permit. This ensures safety standards are met.
Final walk-through: Punch list items like paint touch-ups or cabinet adjustments.
Occupancy permit: Legal approval to live in the home.
Handover: The keys are officially yours!
Factors That Can Speed Up or Delay the Process
While the average Ontario build takes 10–16 months, several factors can influence the timeline:
Weather: Winter builds often face delays from frost or snow.
Permit backlog: Busy building seasons can slow municipal approvals.
Customizations: The more unique the design, the longer it takes.
Material availability: Special finishes or imported materials can delay completion.
Why Fergus & Elora Homeowners Choose LUMA Build Design
At LUMA Build Design, we specialize in custom home building and large-scale renovations across Fergus, Elora, and Centre Wellington. Homeowners choose us because:
We manage the entire process from design to move-in.
We understand local building codes and permit requirements.
We have strong relationships with trusted trades in the area.
We prioritize communication, so you know exactly where your project stands.
Whether you’re planning a farmhouse-style home in Elora, a bungalow home in Elmira or a modern build in Fergus, we provide the expertise and management to bring your vision to life — on time and on budget.
Call us today or reach out directly at our website www.lumabuilddesign.com